The homeowner is ready for the Deck Demolition
Deck Demolition is underway
Back Patio Material Delivered
Housworth Construction is getting ready to begin installing the footers for the patio room addition.
Deck has been removed
Housworth Construction has installed the footers and is now installing the concrete wall to support the brick.
Brick Time for the installers
Once the concrete wall is done, the next step is the brick installation.
Brick Arches Are Being Designed
Housworth Construction's design team created elegant brick arches for the patio base.
Side Brick Arches Are Finished
The brick arches on the side deck are finished, and we are now moving to the back center of the deck.
All Arches Are Completed
We completed the brick archways facing the backyard. This is starting to shape up as an amazing exterior transformation.
The rising of The Columns!
The base of the deck is now completed. We are now entering the column phase of the project.
Scaffolding Is Up
The construction of the column needs scaffolding to proceed.
Custom built arches on top
Housworth Construction has finished the columns and is now building arches on top to enhance the style of this back patio.
Arches are completed
Columns are complete, and Housworth Construction is building arches on top to enhance the style of this back patio.
Brick Steps Now Completed
Back view with all arches completed & brick steps completed.
Roof, Fascia & Soffit Installed
Roof System, Fascia & Soffit are now installed & painted.
Cast Stone Material Are Delivered
Our customer has chosen Cast Stone for the railing system.
Installation Begins with railing system
Cast Stone Installation underway. Our expert masons will see to it that the job is done right.
Railing System Finished
Cast Stone railing system done with the lights inside the bottom of the arches.
Porch creation is complete
The deck has now been transformed into a beautiful extension of the home.